EV Battery Talent in Indonesia: Who to Hire and When

Indonesia's EV battery build-out spans nickel smelters in Sulawesi and Halmahera to cell plants in Karawang. See which leaders each stage needs, and when.

Jessica Baware
By Jessica Baware
Co-Founder & CEO, Jesson Global

Talent acquisition for Indonesia's EV battery industry means hiring along a chain that runs from nickel smelters in Sulawesi and Halmahera to cell plants in Karawang, West Java. The largest current project, the ANTAM-IBC-CBL battery ecosystem, expects 8,000 direct and 35,000 indirect jobs, according to the Cabinet Secretariat. Employers who map leadership roles to each stage, and hire them ahead of commissioning dates, avoid the scramble that follows a plant start-up.

What is the state of Indonesia's EV battery build-out?

Indonesia now has a working battery cell plant, a second integrated project under construction, and the world's largest nickel processing base feeding both. The build-out is real, but it has also changed course, so employers should plan around projects that are funded and on site rather than announcements.

The first cell plant belongs to HLI Green Power, a joint venture of LG Energy Solution and Hyundai Motor Group. The Jakarta Post reports that it launched in 2024 with capacity of up to 10 GWh of cells a year. In April 2025, LG withdrew from a separate, larger battery joint venture worth Rp142 trillion (USD 8.4 billion at the time), citing market conditions and the investment environment, and the government named China's Zhejiang Huayou Cobalt as its replacement. In simple terms, the plant that already makes cells kept running, but the bigger follow-on project changed hands.

The second project broke ground on 29 June 2025. President Prabowo launched the integrated battery ecosystem of the ANTAM-IBC-CBL consortium at Artha Industrial Hills in Karawang, and the Cabinet Secretariat reported the partnership with Chinese investors, while AFP describes the project as backed by China's CATL. The project is a National Strategic Project worth USD 5.9 billion, about Rp107 trillion at the Bank Indonesia JISDOR rate of Rp18,094 on 5 November 2026. It has six sub-projects across East Halmahera and Karawang on 3,023 hectares.

Upstream, Indonesia supplies an estimated 65% of the world's nickel, according to Petromindo, with more than 50 smelters in operation and about 2.5 million tons of nickel a year of smelting capacity at the end of 2025.

Where are the jobs, by stage of the value chain?

Most of the jobs sit upstream in remote industrial parks, while the cell plants sit close to Jakarta. That split shapes everything from relocation packages to how many leaders you can source locally.

AFP's report of the groundbreaking, carried by The Star, breaks the USD 5.9 billion into USD 4.7 billion in Halmahera for mining, smelting and cathode production, and USD 1.2 billion in West Java for battery cell production. So roughly four of every five dollars go to the island end of the chain, far from the capital.

The industrial parks are already large employers. The Indonesia Morowali Industrial Park (IMIP) in Central Sulawesi reported 97,427 active workers in July 2026, plus about 20,000 outsourced workers at contractors, up from 35,592 in 2020. That is about 2.7 times the 2020 workforce in six years.

Downstream, vehicle makers employ fewer people. The Ministry of Industry told a House committee on 9 September 2026 that battery EV investment stood at about Rp30.4 trillion with about 10,650 direct workers across bus, truck, car and two-wheeler producers. Put simply, the single ANTAM-IBC-CBL project plans direct jobs equal to about three quarters of today's whole EV-assembly workforce, so competition for experienced supervisors will come from inside the battery chain itself.

Which leadership roles does each stage need?

Each stage needs a different leadership profile, and the hardest roles combine process expertise with the ability to run large, mixed-nationality teams in remote sites. The table below is a planning map: the locations and projects come from the sources above, and the role lists describe the functions a plant at that stage typically has to fill.

StageMain locationsAnchor projectsLeadership roles to planWhat to test in selection
Nickel miningHalmahera, SulawesiANTAM-IBC-CBL upstream sub-projectsMine general manager, head of mine planning, head of environmentPermit and community experience in remote regions
Smelting (RKEF, HPAL)Morowali, HalmaheraIMIP tenants, ANTAM-IBC-CBLSmelter general manager, head of process, head of K3 (safety)Furnace or autoclave operations, safety record
Precursor and cathodeHalmaheraANTAM-IBC-CBL cathode stagePlant director, quality head, chemical process leadChemical plant start-up, quality systems
Cell manufacturingKarawang, West JavaHLI Green Power, ANTAM-IBC-CBL cell plantPlant director, head of production, head of quality, supply chain headCleanroom or high-volume manufacturing, yield improvement
Pack, vehicle and recyclingAssembly plants nationwideEV makers counted by the Ministry of IndustryEngineering director, aftersales and battery service headLocalisation and supplier development

Two cautions apply to this map. First, the sources give project and workforce totals, not a count of open leadership roles, so treat the table as a checklist rather than a demand forecast. Second, the role mix shifts as plants move from construction to operations, which is why timing matters as much as the role list.

Why does the shift to LFP batteries matter for hiring?

The battery chemistry a plant makes decides which skills it needs, and the market has moved toward lithium iron phosphate (LFP), which uses no nickel. The Jakarta Post reports that LFP reached half of the global EV battery market in 2025, and that more than 90% of EVs sold in Indonesia in 2025 used LFP batteries.

This matters because nickel-based chemistry was the reason for building smelters and precursor plants next to the mines. In plain terms, a cell plant in Java may end up buying or making LFP cells while the nickel chain in Sulawesi sells into other markets, so leaders need to be hired for the chemistry each plant will run, not for the national nickel story.

For hiring managers, this means asking chemistry-specific questions early. A head of production with only nickel-rich cell experience may need a strong LFP deputy, and a smelter leader's experience transfers better to other nickel products than to cell lines.

The upstream side is also slowing new entries. Petromindo reports that Government Regulation No. 28 of 2025 (PP 28/2025) placed a moratorium on new licences for smelters producing ferronickel, nickel pig iron, nickel matte and mixed hydroxide precipitate, while projects already permitted and under construction may proceed. Put simply, the smelter pipeline is now mostly the projects already in the ground, so smelter hiring is about staffing and upgrading existing capacity rather than greenfield teams.

What does safety law mean for plant leaders?

Every plant in this chain must run a formal occupational safety and health management system, and the people who lead it carry real operational weight. Government Regulation No. 50 of 2012 (PP 50/2012) requires a safety and health management system, called SMK3, in every company that employs at least 100 workers or has a high hazard level.

A large smelter or cell plant is likely to meet at least one of these tests, and meeting one is enough. In practice, the head of K3 (safety) is not a compliance clerk; the role needs someone senior enough to stop a line and to be heard by the plant director.

The cost of getting this wrong is documented. On 24 December 2023 a furnace blast at the ITSS smelter in IMIP killed at least 10 Indonesian and 8 Chinese workers and injured 41, according to an IMIP spokesperson quoted by The Jakarta Post. The paper reported that the blast appeared to start when residual slag touched flammable materials during repairs, and that the government increased its scrutiny of work safety amid calls for regular audits. For hiring, this means a candidate's safety record and incident-handling experience should be tested as hard as their production numbers.

How should you time hires to project milestones?

Hire the leaders who design systems before construction ends, and hire the leaders who run shifts before commissioning starts. A search for a senior plant role takes weeks, and notice periods add more, so a hire that starts after the first production run is already late.

Use the milestones your project already tracks:

  1. Final investment decision to early construction. Appoint the plant director or general manager and the head of K3 first. They set the organisation chart, the safety system required by PP 50/2012 and the training plan.
  2. Mid construction. Hire the heads of production, quality, maintenance and supply chain. They need time to write procedures and to select their own managers.
  3. Six months before commissioning. Fill shift managers and senior engineers, and start local training partnerships. IMIP, for example, reports partnerships with Politeknik Industri Logam Morowali, ATI Makassar, Universitas Hasanuddin's vocational metallurgy programme and Universitas Tadulako, covering scholarships, internships and practitioner teaching.
  4. Commissioning and ramp-up. Add continuous-improvement and yield leaders, and review whether expatriate start-up experts have local successors in place.

Put simply, the earlier a leader is in seat, the more of the plant they can shape, and the fewer emergency hires you will need later.

Should you hire local or foreign leaders?

Most projects will need both, at least through start-up, and the realistic goal is a planned handover to Indonesian leaders. The Energy and Mineral Resources Minister, Bahlil Lahadalia, told the groundbreaking that local people should benefit, saying "jadikan anak-anak daerah menjadi tuan di negerinya sendiri", in the Cabinet Secretariat's report. Put simply, the government expects these projects to build local leadership, not only to hire it.

Foreign specialists bring start-up experience from battery and smelter markets that are older than Indonesia's. Indonesian leaders bring regulatory knowledge, community relationships and the ability to retain a local workforce in remote sites. A workable approach is to pair each foreign start-up lead with a named Indonesian deputy from day one, and to write the succession date into both contracts.

Pay data for these roles is thin. We found no tier-1 or tier-2 salary survey that reports battery or smelter executive pay in Indonesia, so benchmark against general manager and plant director data and adjust for remote-site allowances. Our salary benchmark guide explains which published surveys exist and how to read them.

How do you run a search for battery and smelter leaders?

Treat these as specialist searches with a small candidate pool, because the people who have run furnaces, autoclaves or cell lines at scale are few and are mostly employed. That means direct approaches to passive candidates rather than job adverts.

A practical sequence:

  1. Define the outcome, not the title. Write down what the leader must deliver in the first year, such as safe commissioning or a yield target, and the team they inherit.
  2. Map the market by plant, not by job board. List the smelters, industrial parks and cell plants where the relevant experience sits, including neighbouring countries for start-up roles.
  3. Test the hard parts. For site roles, test remote-site leadership and safety incident handling, and for cell plants, test chemistry and yield experience.
  4. Plan relocation early. Halmahera and Morowali roles need a family and rotation package that candidates can evaluate before the final interview.

The same approach applies in other infrastructure-heavy sectors; our guide to data center talent in Indonesia shows how a similar shortage plays out in a different industry. For smelter leadership in particular, our nickel smelter hiring guide goes deeper on site roles and safety. If you are comparing outside partners, our checklist on choosing an executive search firm in Indonesia lists the questions to ask.

Working with Jesson Global

Jesson Global runs executive searches in Indonesia through PT. Jesson Global Indonesia, with sector work that includes mining and industrial, manufacturing and automobile clients. A search is led by a senior consultant, and it typically takes 4 to 8 weeks from kickoff to placement, with a shortlist of 3 to 5 vetted profiles and support for both sides through offer and onboarding. If you are planning leadership hires for a battery or smelter project, you can talk to our recruitment team in Indonesia.

FAQ

How many jobs will Indonesia's EV battery industry create?

There is no single official total for the whole industry. For the largest current project, the ANTAM-IBC-CBL battery ecosystem, the Cabinet Secretariat reported expected employment of 8,000 direct and 35,000 indirect jobs. For comparison, the Ministry of Industry counted about 10,650 direct workers across all battery EV makers in September 2026.

Where are Indonesia's EV battery plants?

Cell manufacturing is in Karawang, West Java, where HLI Green Power operates Indonesia's first cell plant with up to 10 GWh a year of capacity, and where the ANTAM-IBC-CBL cell plant is being built. Upstream mining, smelting and cathode work for that project is in East Halmahera, and the main smelter cluster is in Morowali, Central Sulawesi.

What safety rules apply to battery and smelter plants?

Government Regulation No. 50 of 2012 requires a safety and health management system (SMK3) in every company with at least 100 workers or a high hazard level. Meeting either test is enough, and a large smelter or cell plant is likely to meet at least one. Employers should hire a senior head of K3 early, because that person designs the system before the plant runs.

Do battery projects in Indonesia need foreign experts?

Most projects use foreign specialists for start-up, because Indonesia's battery industry is young. The government has said local people should benefit, so a practical plan pairs each foreign start-up lead with an Indonesian deputy and sets a handover date. Work permit rules for foreign staff should be checked with the Ministry of Manpower before the offer.

How long does it take to hire a battery plant director?

It depends on the market and the candidate's notice period, so plan backwards from commissioning. Jesson Global's own searches typically run 4 to 8 weeks from kickoff to placement, before any notice period. Starting the search before construction ends gives the new director time to build the team.

Is the LG exit a sign that Indonesia's battery plans have stalled?

Not entirely. LG withdrew from a larger joint venture in April 2025, and the government named Huayou as its replacement, while the HLI Green Power cell plant kept operating. The ANTAM-IBC-CBL project broke ground two months later. Employers should plan around projects that are funded and under construction.